Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 60 | 60 | 60 | 0 |
1W236 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश सं0-2062(1)/।।।(2)/13 (प्रा0आ0)/2012 दिनांक 20 मार्च, 2013
TS Amount (lakhs) : 10.36 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
42.00
Resanction Cost :
42.00
Tentative Cost :
42.00
Exp. Upto Last Fy : 4.51
For CFY 2024-2025
Remaining : 37.49
Demand : 0.10
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 4.51
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
11 years 3 months ago
20 Mar 2013
Tentative Completion date:
4 years 3 months ago
31 Mar 2020
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
प्रथम चरण का कार्य पूर्ण दायित्व शेेष। मुआवजा वितरित किया जाना है। -- as on 11-May-2023
Physical Peramenters