Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
1W277 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0 स0 815/।।।(2)/14-57(प्रा0आ0)/13 दिनंाक 08.02.2014
TS Amount (lakhs) : 0.33 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
198.99
Resanction Cost :
198.99
Tentative Cost :
198.99
Exp. Upto Last Fy : 1.00
For CFY 2024-2025
Remaining : 197.99
Demand : 20.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 1.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 years 5 months ago
08 Feb 2014
Tentative Completion date:
4 years 3 months ago
31 Mar 2020
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 11: AIP Division
Bottelneck: no issue
प्रथम चरण का कार्य पूर्ण। सैद्धान्तिक स्वीकृति प्राप्त। एन0पी0वी0 की धनराशि जमा की जा चुकी है। दि्वतीय चरण का आगणन मुख्य अभि्यन्ता के पत्रंाक 2092/101याता0-अ0/19 दिनांक 11.07.2019 लागत रू0 310.17 लाख का शासन स्तर पर प्रेषित है। fवत्त व्यय सfमfत की बैठक माह फरवरी, 2020 में सम्पाfदत, स्वीकृfत अपेfक्षत। -- as on 30-Nov-2020
Physical Peramenters