Work Profile Report [1W278]
Fin Plan
Tenders
Aggrements
alerts
Documents
Samples
Administrative Approval Detail : श्शा0 स0 815/।।।(2)/14-57(प्रा0आ0)/13 दिनंाक 08.02.2014
TS Amount (lakhs) : 0.44 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
32.47
Resanction Cost :
32.47
Tentative Cost :
0.10
Saving
32.37
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
32.37
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Unstarted Work
Sanction on : 11 years 11 months ago
08 Feb 2014
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
ग्रामवासी अपनी निजी भूमि इस मार्ग हेतु दिेये जाने में आपत्ति कर रहे हैं। -- as on 02-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: