Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 6 | 0 |
1W281 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0 स0 815/।।।(2)/14-57(प्रा0आ0)/13 दिनंाक 08.02.2014
TS Amount (lakhs) : 0.66 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
48.71
Resanction Cost :
48.71
Tentative Cost :
48.71
Exp. Upto Last Fy : 25.65
For CFY 2024-2025
Remaining : 23.06
Demand : 0.20
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 25.65
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 years 5 months ago
08 Feb 2014
Tentative Completion date:
4 years 3 months ago
31 Mar 2020
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 12: AIP DM
Bottelneck: no issue
प्रथम चरण का कार्य पूर्ण दायित्व शेष। कार्य के द्वितीय चरण की स्वीकृति प्राप्त, जिस पर कार्य प्रगति पर है। -- as on 31-Jul-2020
Physical Peramenters