Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
1W361 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश सं0 6098/।।।(2)/15-13(मु0मं0 घो0) /2015 दिनांक 18.08.2015
TS Amount (lakhs) : 137.57 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
137.57
Resanction Cost :
137.57
Tentative Cost :
137.57
Exp. Upto Last Fy : 91.64
For CFY 2024-2025
Remaining : 45.93
Demand : 10.00
Allotment : 0.00
Exp in CFY : 1.56
Total Up to Date Exp : 93.20
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
8 years 10 months ago
18 Aug 2015
Tentative Completion date:
3 years 3 months ago
31 Mar 2021
Actual Completion Date:
3 years 4 months ago
01 Mar 2021
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
कार्य्र पूर्ण माह 03ध्2021 दायित्व शेष। -- as on 11-May-2023
Physical Peramenters