Work Profile Report [1W37]
Fin Plan
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 59/लो.नि.-2/04-41(प्रा0 आ0)/03 दिनांक 22.1.2004
TS Amount (lakhs) : 28.07 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
41.70
Resanction Cost :
41.70
Tentative Cost :
41.70
Exp. Upto Last Fy :
22.04
For CFY 2024-2025
Remaining :
19.66
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
22.04
Work completed
Sanction on : 21 years 2 weeks ago
21 Jan 2004
Physical Progress:
At start of FY 2024-2025 :
76 %
Up to Date :
100 %
Tentative Completion date on : 2 years 10 months ago
31 Mar 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष। -- as on 26-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand