Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 15 | 15 | 15 | 0 |
1W375 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0 संख्या 1218/।।।(2)/16-53(एम0एल0ए0) /2015 दिनांक 27 जून, 2016
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
0.90
Resanction Cost :
0.90
Tentative Cost :
0.90
Exp. Upto Last Fy : 0.09
For CFY 2024-2025
Remaining : 0.81
Demand : 0.82
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.09
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 years 2 weeks ago
27 Jun 2016
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्थल चयन प्रस्ताव अधीक्षण अभियन्ता के पत्रांक 2996/903सी0-01/20 दिनंाक 04.09.2020 द्वारा स्थल चयन प्रस्ताव अनुमोदित। -- as on 30-Sep-2020
Physical Peramenters