Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 1.500 | 4.5 | 2.500 | 0.000 |
1W378 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0 संख्या 2008/।।।(2)/16-53(एम0एल0ए0) /2015 दिनांक 27 जून, 2016
TS Amount (lakhs) : 148.45 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
392.31
Resanction Cost :
392.31
Tentative Cost :
392.31
Exp. Upto Last Fy : 136.25
For CFY 2024-2025
Remaining : 256.06
Demand : 25.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 136.25
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 80 %
Sanction on :
8 years 2 weeks ago
27 Jun 2016
Tentative Completion date:
2 years 2 weeks ago
30 Jun 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पार्ट-।। 4.50 कि.मी. लम्बाई के सापेक्ष 2.00 कि.मी0 कार्य पूर्ण शेष कार्य प्रगति पर। -- as on 03-Jul-2024
Physical Peramenters