Work Profile Report [1W40]

ज्वारनैणी से बक्सवाड़ मोटर मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 2454/।।।-02/05-07 प्रा0आ0/05 टी0सी0 दि0 28.़10.05 ( मु0म0घो0)

TS Amount (lakhs) : 139 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

139.00

Resanction Cost :

559.03

Tentative Cost :

559.03

Exp. Upto Last Fy :

108.30

For CFY 2025-2026

Remaining :

450.73

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

108.30

Work completed

Sanction on : 19 years 5 months ago

28 Oct 2005

Physical Progress:

At start of FY 2025-2026 :

80 %

Up to Date :

40 %

Tentative Completion date on : 5 years 6 days ago

31 Mar 2020

Actual Completion Date : 5 years 11 months ago

01 May 2019

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
10
10
-

Remark

view all

4.00 कि0मी0 लम्बाई में कार्य 05/2019 में पूर्ण शेष 6.00 कि0मी0 लम्बाई में विधिवत् स्वीकृति प्राप्त करने हेतु एन0पी0वी0 की धनराशि जमा की जा चुकी है तथा प्रकरण में प्राप्त आपत्तियों के निराकरण के उपरान्त इस कार्यालय के पत्रांक 1710/7सी0 दिनांक 15.07.2024 द्वारा प्रभागीय वनाधिकारी चम्पावत वन प्रभाग, चम्पावत को प्रेषित किया जा चुका है। -- as on 18-Jul-2024

Rating : 40

Forest Case Pending At : 14: AIP Conservator

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: