Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8.000 | 0 | 0.000 | 0.000 |
1W430 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश संख्या 426/।।।(2)/18-02(प्रा0आ0) /2018 दिनंाक 09 मार्च, 2018
TS Amount (lakhs) : 492.72 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
492.72
Resanction Cost :
492.72
Tentative Cost :
492.72
Exp. Upto Last Fy : 472.70
For CFY 2024-2025
Remaining : 20.02
Demand : 9.00
Allotment : 9.00
Exp in CFY : 8.04
Total Up to Date Exp : 480.74
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 4 months ago
09 Mar 2018
Tentative Completion date:
2 years 10 months ago
20 Aug 2021
Actual Completion Date:
2 years 11 months ago
03 Aug 2021
Remark
Bottelneck: no issue
कार्य पूर्ण माह 08/2021 दायित्व शेष। -- as on 11-May-2023