Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 1.500 | 1.5 | 1.000 | 0.000 |
1W44 :
Administrative Approval Detail : Go no-774/111(2)/06-13प्रा.आ./06 दि0 28.3.06 &E file no 45610 दि0 29.03.2023
TS Amount (lakhs) : 112.38 Lacs
Financial Detail
Sanction Cost : 53.40 Lacs
Resanction Cost : 281.16 Lacs
Exp. Upto Last Fy : 87.16 Lacs
For CFY 2024-2025
Remaining : 194.00 Lacs
Demand : 50.00 Lacs
Allotment : 15.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 87.16 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
18 years 1 month ago
28 Mar 2006
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
मूल स्वीकृति के सापेक्ष 3.00 कि0मी0 पहाड़ कटान का कार्य पूर्ण। पार्ट ।। कार्य 1.20 कि0मी0 पूर्ण शेष कार्य प्रगति पर। -- as on 06-Mar-2024
Physical Peramenters