Work Profile Report [1W44]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : Go no-774/111(2)/06-13प्रा.आ./06 दि0 28.3.06 &E file no 45610 दि0 29.03.2023
TS Amount (lakhs) : 112.38 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.40
Resanction Cost :
281.16
Tentative Cost :
281.16
Exp. Upto Last Fy :
87.16
For CFY 2024-2025
Remaining :
194.00
Demand :
130.00
Allotment :
25.00
Exp in CFY :
54.07
Total Up to Date Exp :
141.23
Construction Started
Sanction on : 18 years 7 months ago
28 Mar 2006
Physical Progress:
At start of FY 2024-2025 :
40 %
Up to Date :
40 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मूल स्वीकृति के सापेक्ष 3.00 कि0मी0 पहाड़ कटान का कार्य पूर्ण। पार्ट ।। कार्य 1.20 कि0मी0 पूर्ण शेष कार्य प्रगति पर। -- as on 06-Mar-2024
Assets :
© PWD Uttarakhand