Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
1W459 :
Administrative Approval Detail : श्शा0 संख्य 709(ए)/।।।(2)/19-51 (एम0एल0ए0)/2017 टी0सी0 दिनंाक 18 फरवरी, 2019
TS Amount (lakhs) : 184.55 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
184.55
Resanction Cost :
184.55
Tentative Cost :
184.55
Exp. Upto Last Fy : 157.43
For CFY 2024-2025
Remaining : 27.12
Demand : 4.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 157.43
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
18 Feb 2019
Tentative Completion date:
3 years 5 months ago
31 Jan 2021
Actual Completion Date:
3 years 6 months ago
01 Jan 2021
Remark
Bottelneck: no issue
कार्य पूर्ण माह 01/2021 दायित्व शेष। -- as on 31-Jan-2021
Physical Peramenters