Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1 | 0 |
1W491 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश सं0 478/।।।(2)/20-52(एम0एल0 ए0)/2017
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
4.24
Resanction Cost :
4.24
Tentative Cost :
4.24
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 4.14
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
4 years 5 months ago
30 Jan 2020
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
समरेखण प्रस्ताव अधीक्षण अभियन्ता, प्रथम वृत्त, लो0नि0वि0, अल्मोड़ा के पत्रांक 264/703सी0-01/20 दिनंाक 05.02.2021 द्वारा अनुमोदित। -- as on 28-Feb-2021
Physical Peramenters