Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
1W522 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी अल्मोड़ा के पत्रांक 1067/fज0यो0/2020-21 fदनंाक 12.11.2020
TS Amount (lakhs) : 5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
13.00
Resanction Cost :
13.00
Tentative Cost :
13.00
Exp. Upto Last Fy : 10.89
For CFY 2024-2025
Remaining : 2.11
Demand : 2.11
Allotment : 2.11
Exp in CFY : 0.00
Total Up to Date Exp : 10.89
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
3 years 8 months ago
12 Nov 2020
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
2 years 3 months ago
31 Mar 2022
Remark
Bottelneck: no issue
कार्य पूर्ण ( 31-03-2022)।दायित्व अवशेष। -- as on 05-Jul-2024
Physical Peramenters