Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.8 | 3.8 | 0.000 | 3.8 | 0.000 | 0.000 |
1W539 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश सं0 1341/।।।(2)/21-52(एम0एल0ए0)/2015 दिनांक 13.05.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
85.08
Resanction Cost :
85.08
Tentative Cost :
85.08
Exp. Upto Last Fy : 66.32
For CFY 2024-2025
Remaining : 18.76
Demand : 5.00
Allotment : 0.00
Exp in CFY : 3.27
Total Up to Date Exp : 69.59
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 2 months ago
13 May 2021
Tentative Completion date:
2 years 3 months ago
30 Mar 2022
Actual Completion Date:
1 year 6 months ago
22 Dec 2022
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
कार्य पूर्ण माह 03/2022 दायित्व शेष। -- as on 11-May-2023
Physical Peramenters