Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
1W542 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : जिलाधिकारी अल्मोड़ा का पत्रांक 180(।)/जि0यो0 /2021-22 दिनांक 31.05.2021
TS Amount (lakhs) : 17 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
17.00
Resanction Cost :
17.00
Tentative Cost :
17.00
Exp. Upto Last Fy : 15.18
For CFY 2024-2025
Remaining : 1.82
Demand : 1.82
Allotment : 1.82
Exp in CFY : 1.80
Total Up to Date Exp : 16.98
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
3 years 1 month ago
31 May 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में है। -- as on 05-Jul-2024