Work Profile Report [1W565]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 3282/।।।(2)/21-51(एम0एल0ए0)/2017टी0सी0 ।। दिनांक 10.09.2021
TS Amount (lakhs) : 97.36 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
97.36
Resanction Cost :
97.36
Tentative Cost :
72.45
Saving
24.91
Exp. Upto Last Fy :
60.28
For CFY 2025-2026
Remaining :
37.08
Demand :
12.17
Allotment :
6.67
Exp in CFY :
6.67
Total Up to Date Exp :
66.95
Work completed
Sanction on : 4 years 3 months ago
10 Sep 2021
Physical Progress:
At start of FY 2025-2026 :
90 %
Up to Date :
100 %
Tentative Completion date on : 2 years 8 months ago
01 Apr 2023
Actual Completion Date : 2 years 8 months ago
01 Apr 2023
Physical Linear Components
Remark
Work Complete. -- as on 19-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: