Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
1W565 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 3282/।।।(2)/21-51(एम0एल0ए0)/2017टी0सी0 ।। दिनांक 10.09.2021
TS Amount (lakhs) : 97.36 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
97.36
Resanction Cost :
97.36
Tentative Cost :
97.36
Exp. Upto Last Fy : 55.46
For CFY 2024-2025
Remaining : 41.90
Demand : 10.00
Allotment : 0.00
Exp in CFY : 1.11
Total Up to Date Exp : 56.57
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
2 years 10 months ago
10 Sep 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
1 year 3 months ago
01 Apr 2023
Remark
Forest Status 01: Withdraw
Bottelneck: Other Reason
पहाड़ कटान कार्य 4.50 कि0मी0 पूर्ण शेष 0.50 कि0मी0 लम्बाई में ग्रामवासियों द्वारा पानी का श्रोत क्षतिग्रस्त होने से बचाने हेतु सुरक्षात्मक कार्य कराये जाने तक कार्य करने में बाधा उत्पन्न किये जाने के कारण मार्ग निर्माण 4.50 कि0मी0 में ही समाप्त किये जाने का निर्णय सर्वसम्मति से लिया गया है। पार्ट-।। की स्वीकृति के अन्तर्गत उक्त जल श्रोत हेतु सुरक्षात्मक कार्य का प्राविधान किया जायेगा। -- as on 31-Oct-2023
Physical Peramenters