Work Profile Report [1W568]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन का पत्राक 6182 /III (2)/21-51/(ऍम०ऍल०ए०)/2015 dated 22-12-2021
TS Amount (lakhs) : 206.91 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
206.91
Resanction Cost :
206.91
Tentative Cost :
206.91
Exp. Upto Last Fy :
193.49
For CFY 2024-2025
Remaining :
13.42
Demand :
1.50
Allotment :
1.50
Exp in CFY :
0.00
Total Up to Date Exp :
193.49
In Maintenance After Completion
Sanction on : 2 years 10 months ago
22 Dec 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 1 week ago
31 Oct 2023
Actual Completion Date : 1 year 3 weeks ago
20 Oct 2023
Physical Linear Components
Remark
कार्य पूर्ण माह 10/2023 -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: