Work Profile Report [1W571]
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : GO letter no1565/III(2)/21-52(MLA)/2017 दिनांक 15-06-2017
TS Amount (lakhs) : 54.11 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
54.11
Resanction Cost :
54.11
Tentative Cost :
54.11
Exp. Upto Last Fy :
33.25
For CFY 2024-2025
Remaining :
20.86
Demand :
9.00
Allotment :
9.48
Exp in CFY :
9.48
Total Up to Date Exp :
42.73
Construction Started
Sanction on : 7 years 6 months ago
15 Jun 2017
Physical Progress:
At start of FY 2024-2025 :
25 %
Up to Date :
90 %
Tentative Completion date on : 3 months 5 days from now
30 Mar 2025
Actual Completion Date : 2 years 2 months ago
19 Oct 2022
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 02-May-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand