Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 2 | 2 | 2 | 0 | ||
Span of Bridges [m] | 42 | 42 | 42 | 0 |
1W574 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : GO letter no 4714/III(2)/21-52(MLA)/2017 दिनांक 04-10-2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
12.60
Resanction Cost :
12.60
Tentative Cost :
12.60
Exp. Upto Last Fy : 7.74
For CFY 2024-2025
Remaining : 4.86
Demand : 2.10
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 7.74
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 9 months ago
04 Oct 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
अधीक्षण अभियन्ता प्रथम वृत्त, लो0नि0वि0, अल्मोड़ा के पत्रांक 3838/928सी0-01/22 दिनांक 16.09.2022 द्वारा समरेखण अनुमोदित। मार्ग का संयुक्त निरीक्षण कर लिया गया है। वन भूमि हस्तान्तरण प्रस्ताव गठित किया जा रहा है। -- as on 10-May-2023
Physical Peramenters