Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.5 | 0 | ||
No of Bridges | 2 | 2 | 2 | 0 | ||
Span of Bridges [m] | 25 | 25 | 25 | 0 |
1W578 :
Administrative Approval Detail : GO no 580/III(2)/21-51/ऍम० एल० ए०/2017/टी० सी० dated 31-12-2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
54.65
Resanction Cost :
54.65
Tentative Cost :
54.65
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 54.65
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 6 months ago
31 Dec 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
मार्ग का सवेक्षण कार्य पूर्ण। समरेखण प्रस्ताव गठित करने की कार्यवाही की जा रही है। -- as on 07-Aug-2023
Physical Peramenters