Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 18 | 18 | 0.000 | 18 | 18.000 | 0.000 |
1W584 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : GO letter no 2390/III(2)/21-52(MLA)/2017 TC दिनांक 04-08-2021
TS Amount (lakhs) : 166.26 Lacs
Financial Detail
Sanction Cost : 166.26 Lacs
Resanction Cost : 166.26 Lacs
Exp. Upto Last Fy : 106.69 Lacs
For CFY 2024-2025
Remaining : 59.57 Lacs
Demand : 50.00 Lacs
Allotment : 10.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 106.69 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 35 %
Sanction on :
2 years 9 months ago
04 Aug 2021
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
दोनों ओर की राफ्ट का कार्य पूर्ण व बायी ओर के एबेटमेन्ट 4.00 मीटर ऊचाई एवं दायी ओर का एबटमेट 2.00 मीटर ऊचाई में कास्टिंग का कार्य पर्ण शेष कार्य प्रगति पर। -- as on 06-Mar-2024
Physical Peramenters