Work Profile Report [1W586]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 - ई फाई संख्या 46885 दिनंाक 03 मार्च, 2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
223.86
Resanction Cost :
223.86
Tentative Cost :
223.86
Exp. Upto Last Fy :
81.81
For CFY 2024-2025
Remaining :
142.05
Demand :
110.00
Allotment :
72.39
Exp in CFY :
72.39
Total Up to Date Exp :
154.20
Work completed
Sanction on : 1 year 9 months ago
03 Mar 2023
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
100 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
4.00 Km लम्बाई में पार्ट-।। का कार्य पूर्ण, शेष कार्य प्रगति पर। -- as on 25-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: