Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 2.000 | 2 | 2.000 | 0.000 |
1W586 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 - ई फाई संख्या 46885 दिनंाक 03 मार्च, 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 223.86 Lacs
Resanction Cost : 223.86 Lacs
Exp. Upto Last Fy : 81.81 Lacs
For CFY 2024-2025
Remaining : 142.05 Lacs
Demand : 50.00 Lacs
Allotment : 15.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 81.81 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
1 year 2 months ago
03 Mar 2023
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
दीवार निर्माण तथा स्कपर निर्माण का कार्य किया जा रहा है | 2.00 लम्बाई में पार्ट-।। का कार्य पूर्ण, शेष कार्य प्रगति पर। -- as on 09-Feb-2024
Physical Peramenters