Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 2.000 | 2 | 2.000 | 0.000 |
1W586 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 - ई फाई संख्या 46885 दिनंाक 03 मार्च, 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
223.86
Resanction Cost :
223.86
Tentative Cost :
223.86
Exp. Upto Last Fy : 81.81
For CFY 2024-2025
Remaining : 142.05
Demand : 110.00
Allotment : 28.00
Exp in CFY : 0.84
Total Up to Date Exp : 82.65
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 75 %
Sanction on :
1 year 4 months ago
03 Mar 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 01: Withdraw
Bottelneck: no issue
3.00 Km लम्बाई में पार्ट-।। का कार्य पूर्ण, शेष कार्य प्रगति पर। -- as on 11-Jul-2024
Physical Peramenters