Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 2.500 | 0.000 |
1W587 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 - ई फाई संख्या 38879 दिनंाक 10-11-2022
TS Amount (lakhs) : 187.14 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
187.14
Resanction Cost :
187.14
Tentative Cost :
187.14
Exp. Upto Last Fy : 104.26
For CFY 2024-2025
Remaining : 82.88
Demand : 60.00
Allotment : 60.00
Exp in CFY : 38.17
Total Up to Date Exp : 142.43
Work completed
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 100 %
Sanction on :
1 year 8 months ago
10 Nov 2022
Tentative Completion date:
3 months 1 day from now
19 Oct 2024
Actual Completion Date:
1 month 2 days ago
15 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण माह 06/2024 दायित्व शेष। -- as on 03-Jul-2024
Physical Peramenters