Work Profile Report [1W598]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी अल्मोड़ा का पत्र संख्या 800/जिला योजना/अर्थ एवं संख्या/लो0नि0वि0/2022-23 दिनांक 28.09.2022
TS Amount (lakhs) : 15 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
15.00
Resanction Cost :
15.00
Tentative Cost :
15.00
Exp. Upto Last Fy :
14.02
For CFY 2024-2025
Remaining :
0.98
Demand :
0.98
Allotment :
0.98
Exp in CFY :
0.00
Total Up to Date Exp :
14.02
Construction Started
Sanction on : 2 years 1 month ago
28 Sep 2022
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
50 %
Tentative Completion date on : 4 months 2 weeks from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 02-May-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand