Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 36.4 | 36.4 | 36.4 | 0 |
1W645 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 212/।।।(2)/2024-01 (प्रा0आ0)/2023 दिनंाक 31.03.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
328.59
Resanction Cost :
328.59
Tentative Cost :
328.59
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 328.59
Demand : 328.59
Allotment : 60.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 20-Jun-2024
Physical Peramenters