Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 6.1 | 6.1 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 10 | 10 | 10 | 0 |
1W65 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2454/।।।-02/05-07 प्रा0आ0/05 टी0सी0 दि0 28.़10.05 ( मु0म0घो0)
TS Amount (lakhs) : 106 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
106.00
Resanction Cost :
106.00
Tentative Cost :
106.00
Exp. Upto Last Fy : 100.93
For CFY 2024-2025
Remaining : 5.07
Demand : 5.07
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 100.93
Construction Started
Physical Progress:
At start of FY 2024-2025 : 76 %
Up to Date : 76 %
Sanction on :
18 years 8 months ago
28 Oct 2005
Tentative Completion date:
8 months 1 week from now
30 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status ---
Bottelneck: no issue
पार्ट-।। कार्य पूर्ण। सेतु कार्य किया जाना है। -- as on 31-Mar-2021
Physical Peramenters