Work Profile

1W65 :

No Pic Avilable Time series Gantt
गोलूछीना गल्ली बस्यूरा गोबिन्दपुर मो0मा0 (10मी0 आर0सी0सी0 सेतु)


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शा0सं0 2454/।।।-02/05-07 प्रा0आ0/05 टी0सी0 दि0 28.़10.05 ( मु0म0घो0)

TS Amount (lakhs) : 106 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

106.00

Resanction Cost :

106.00

Tentative Cost :

106.00

Exp. Upto Last Fy : 100.93

For CFY 2024-2025

Remaining : 5.07

Demand : 5.07

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 100.93

Construction Started

Physical Progress:

At start of FY 2024-2025 : 76 %

Up to Date : 76 %

Sanction on :
18 years 8 months ago
28 Oct 2005


Tentative Completion date:
8 months 1 week from now
30 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 103

Remark

Forest Status ---

Bottelneck: no issue


पार्ट-।। कार्य पूर्ण। सेतु कार्य किया जाना है। -- as on 31-Mar-2021

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 7 6.1 6.1 0
No of Bridges 1 1 1 0
Span of Bridges [m] 10 10 10 0
Currently only Bank Gaurantee information is avilable