Work Profile Report [1W661]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E - File No. 48456
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
403.19
Resanction Cost :
403.19
Tentative Cost :
403.19
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
403.19
Demand :
403.19
Allotment :
80.00
Exp in CFY :
2.53
Total Up to Date Exp :
2.53
Construction Started
Sanction on : 9 months 2 weeks ago
07 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
5 %
Tentative Completion date on : 6 months 5 days from now
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दिनंाक 23.11.2024 को अनुबन्ध गठित। कार्य प्रगति पर। -- as on 04-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: