Work Profile Report [1W661]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E - File No. 48456
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
403.19
Resanction Cost :
403.19
Tentative Cost :
403.19
Exp. Upto Last Fy :
2.53
For CFY 2025-2026
Remaining :
400.66
Demand :
0.00
Allotment :
80.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.53
Construction Started
Sanction on : 1 year 4 weeks ago
07 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
25 %
Tentative Completion date on : 4 months 2 weeks from now
22 Aug 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
दि0 23.11.2024 को अनुबन्ध गठित। कार्य प्रगति पर। -- as on 22-Feb-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: