Work Profile

1W67 :

No Pic Avilable Time series Gantt
गोलूछीना-श्रीखेत मोटर मार्ग का भिटारकोट तक विस्तार


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शा0सं0 2555/।।। (2)/ (प्रा0आ0-41) प्रा0 आ0 दिनांक 26.09.06

TS Amount (lakhs) : 89 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

89.00

Resanction Cost :

89.00

Tentative Cost :

89.00

Exp. Upto Last Fy : 79.32

For CFY 2024-2025

Remaining : 9.68

Demand : 10.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 79.32

Work completed

Physical Progress:

At start of FY 2024-2025 : 100 %

Up to Date : 100 %

Sanction on :
17 years 9 months ago
26 Sep 2006


Tentative Completion date:
3 years 3 months ago
31 Mar 2021


Actual Completion Date:
3 years 4 months ago
01 Mar 2021


Rating : 100

Remark

Forest Status 21: Final

Bottelneck: no issue


कार्य पूर्ण माह 03/2021 दायित्व शेष। -- as on 31-Mar-2021

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 5 3 3 0
Currently only Bank Gaurantee information is avilable