Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 3 | 3 | 0 |
1W67 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2555/।।। (2)/ (प्रा0आ0-41) प्रा0 आ0 दिनांक 26.09.06
TS Amount (lakhs) : 89 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
89.00
Resanction Cost :
89.00
Tentative Cost :
89.00
Exp. Upto Last Fy : 79.32
For CFY 2024-2025
Remaining : 9.68
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 79.32
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
17 years 9 months ago
26 Sep 2006
Tentative Completion date:
3 years 3 months ago
31 Mar 2021
Actual Completion Date:
3 years 4 months ago
01 Mar 2021
Remark
Forest Status 21: Final
Bottelneck: no issue
कार्य पूर्ण माह 03/2021 दायित्व शेष। -- as on 31-Mar-2021
Physical Peramenters