Work Profile Report [1W686]

पाण्डेखोला में सी0एम0ओ0 को जाने वाला रास्ता
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : जिलाधिकारी अल्मोड़ा का पत्र सं0 403ध्(लोक निर्माण विभाग)ध्जि0यो0ध्2023-24 दिनंाक 21.06.2023

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

5.01

Resanction Cost :

5.01

Tentative Cost :

5.01

Exp. Upto Last Fy :

4.44

For CFY 2025-2026

Remaining :

0.57

Demand :

0.00

Allotment :

5.01

Exp in CFY :

0.00

Total Up to Date Exp :

4.44

Work completed

Sanction on : 1 year 9 months ago

21 Jun 2023

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 1 year 6 days ago

31 Mar 2024

Actual Completion Date : 1 year 6 days ago

31 Mar 2024

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Jobs
1
1
1
-

Remark

view all

कार्य पूर्ण ।दायित्व अवशेष। -- as on 05-Jul-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand