Work Profile

1W70 :

No Pic Avilable Time series Gantt
कठपुड़िया बंगसर मोटर मार्ग का निर्माण


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शा0सं0 764/।।।(2)/08-65 (प्रा0आ0) / 07 दिनंाक 24.03.2008

TS Amount (lakhs) : 105 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

105.00

Resanction Cost :

105.00

Tentative Cost :

105.00

Exp. Upto Last Fy : 0.74

For CFY 2024-2025

Remaining : 104.26

Demand : 5.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 0.74

Construction Started

Physical Progress:

At start of FY 2024-2025 : 25 %

Up to Date : 25 %

Sanction on :
16 years 3 months ago
24 Mar 2008


Tentative Completion date:
8 months 1 week from now
31 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 27

Remark

Forest Status 18: Final Approval

Bottelneck: no issue


1 कि0मी0 पहाड़ कटान एवं पार्ट-।। का कार्य पूर्ण। अवशेष कार्य विधिवत् स्वीकृति प्राप्त -- as on 12-Apr-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 3 3 1.000 2 0.500 0.000
Currently only Bank Gaurantee information is avilable