Work Profile Report [1W70]

कठपुड़िया बंगसर मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 764/।।।(2)/08-65 (प्रा0आ0) / 07 दिनंाक 24.03.2008

TS Amount (lakhs) : 105 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

105.00

Resanction Cost :

105.00

Tentative Cost :

83.49

Saving

21.51

Exp. Upto Last Fy :

23.88

For CFY 2025-2026

Remaining :

81.12

Demand :

59.61

Allotment :

50.84

Exp in CFY :

50.84

Total Up to Date Exp :

74.72

Construction Started

Sanction on : 17 years 9 months ago

24 Mar 2008

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

92 %

Tentative Completion date on : 2 months 3 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
3
1.500
1.5
0.250
0.000

Remark

view all

Overall Saving 21.51 has been recorded as expected cost of work reduced from 105 to 83.49 . -- as on 19-Dec-2025

Rating : 90

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© 2026 PWD Uttarakhand