Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 1.000 | 2 | 0.500 | 0.000 |
1W70 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 764/।।।(2)/08-65 (प्रा0आ0) / 07 दिनंाक 24.03.2008
TS Amount (lakhs) : 105 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
105.00
Resanction Cost :
105.00
Tentative Cost :
105.00
Exp. Upto Last Fy : 0.74
For CFY 2024-2025
Remaining : 104.26
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.74
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
16 years 3 months ago
24 Mar 2008
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
1 कि0मी0 पहाड़ कटान एवं पार्ट-।। का कार्य पूर्ण। अवशेष कार्य विधिवत् स्वीकृति प्राप्त -- as on 12-Apr-2024
Physical Peramenters