Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 0.000 |
1W704 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाईल सं0 50429
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
152.79
Resanction Cost :
152.79
Tentative Cost :
152.79
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 152.79
Demand : 100.00
Allotment : 44.50
Exp in CFY : 44.05
Total Up to Date Exp : 44.05
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 90 %
Sanction on :
1 year 1 month ago
18 May 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
work is in progress -- as on 15-Jun-2024
Physical Peramenters