Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
1W84 :
Administrative Approval Detail : शा0स0 830/।।।(2)/ 08-29(प्रा0आ0)/07 दिनांक 24.03.2008
TS Amount (lakhs) : 98.54 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
117.00
Resanction Cost :
117.00
Tentative Cost :
117.00
Exp. Upto Last Fy : 55.00
For CFY 2024-2025
Remaining : 62.00
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 55.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
16 years 3 months ago
24 Mar 2008
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
पहाड़ कटान एवं पार्ट-।। का कार्य 1.75 कि0मी0 पूर्ण शेष कार्य प्रगति पर। -- as on 16-Dec-2023
Physical Peramenters