Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 1.5 | 1.5 | 0 |
1W92 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 1607/।।।(2) 105-53 (प्रा0आ0)/05 दिनांक 12.08.05
TS Amount (lakhs) : 41.7 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
41.70
Resanction Cost :
41.70
Tentative Cost :
41.70
Exp. Upto Last Fy : 40.28
For CFY 2024-2025
Remaining : 1.42
Demand : 1.20
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 40.28
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
18 years 11 months ago
12 Aug 2005
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण शेष कार्य प्रगति पर। -- as on 11-May-2023
Physical Peramenters