Work Profile

1W92 :

No Pic Avilable Time series Gantt
नौगांव पनौरा मार्ग


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शा0 सं0 1607/।।।(2) 105-53 (प्रा0आ0)/05 दिनांक 12.08.05

TS Amount (lakhs) : 41.7 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

41.70

Resanction Cost :

41.70

Tentative Cost :

41.70

Exp. Upto Last Fy : 40.28

For CFY 2024-2025

Remaining : 1.42

Demand : 1.20

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 40.28

Construction Started

Physical Progress:

At start of FY 2024-2025 : 40 %

Up to Date : 40 %

Sanction on :
18 years 11 months ago
12 Aug 2005


Tentative Completion date:
8 months 1 week from now
31 Mar 2025


Actual Completion Date:
Not Yet Reported


Rating : 104

Remark

Forest Status 21: Final

Bottelneck: no issue


पहाड़ कटान का कार्य पूर्ण शेष कार्य प्रगति पर। -- as on 11-May-2023

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 3 1.5 1.5 0
Currently only Bank Gaurantee information is avilable