Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
20W241 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 2228 /।।। (2) / 17-45 (एम0एल0ए0)/2017 दि0 13 सितम्बर 2017
TS Amount (lakhs) : 5 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
64.40
Resanction Cost :
64.40
Tentative Cost :
64.40
Exp. Upto Last Fy : 11.69
For CFY 2024-2025
Remaining : 52.71
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 11.69
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
6 years 9 months ago
13 Oct 2017
Tentative Completion date:
7 months 4 weeks from now
15 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग निर्माण कार्य पूर्ण । नाप भूमि का मुआवजा प्रपत्र तैयार किये जा रहे है। -- as on 10-Aug-2023
Physical Peramenters