Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 0.000 | 8 | 0.000 | 0.000 |
20W324 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 560/।।। (2) /19-45 (एम0एल0ए0) / 2017 दि0 01-फरवरी 2019
TS Amount (lakhs) : 9.11 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
36.80
Resanction Cost :
36.80
Tentative Cost :
36.80
Exp. Upto Last Fy : 8.20
For CFY 2024-2025
Remaining : 28.60
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 8.20
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
5 years 5 months ago
01 Feb 2019
Tentative Completion date:
1 year 3 months from now
31 Oct 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
04 किमी0 लम्बाई में द्वितीय चरण स्टेज-। का कार्य पूर्ण । शेष 4 किमी0 में वनभूमि प्रस्ताव तैयार करने हेतु संयुक्त निरीक्षण किया जाना है। -- as on 21-Nov-2023
Physical Peramenters