Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 80 | 36 | 0.000 | 36 | 0.000 | 0.000 |
20W33 :
Work not linked with IM
Bridges on The Basis of AI: Pedestrain bridge onJhulaghat Bridle Path
Administrative Approval Detail : शा० सं० 572/111 -2/06 -08 (प्रा0आ0) /06 दि0 28/3/06 एवं ई-फाइल सं० -44765 दि0 02-09-2023
TS Amount (lakhs) : 44.73 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
417.38
Resanction Cost :
999.05
Tentative Cost :
999.05
Exp. Upto Last Fy : 76.52
For CFY 2024-2025
Remaining : 922.53
Demand : 200.00
Allotment : 45.00
Exp in CFY : 42.69
Total Up to Date Exp : 119.21
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 52 %
Sanction on :
18 years 4 months ago
28 Feb 2006
Tentative Completion date:
1 year 4 months from now
16 Dec 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
5.00 किमी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण । शेष प्रगति में है। -- as on 10-Jun-2024
Physical Peramenters