Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
20W391 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन सं0 620/।।। (2) /21-45 (एम0एल0ए0) /2017 टी0सी0 । दिनाॅक 20 मार्च 2021
TS Amount (lakhs) : 58.73 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
58.73
Resanction Cost :
58.73
Tentative Cost :
58.73
Exp. Upto Last Fy : 40.76
For CFY 2024-2025
Remaining : 17.97
Demand : 17.97
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 40.76
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 3 months ago
20 Mar 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इस कार्य में 3 किमी0 मोटर मार्ग में नव निर्माण स्टेज-। की स्वीकृति प्राप्त है जिसके सापेक्ष मार्ग में पहाड़ कटान का कार्य पूर्ण । मोडों पर ग्रेड सुधार किया जा रहा है। अधिकांश स्थानों पर कार्य कर लिया गया है। तथा किमी0 3 में 1 से 2 स्थानों पर सुधार कार्य किया जाना अपेक्षित है। -- as on 29-Jun-2024