Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 3.000 | 9 | 4.000 | 2.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
20W40 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 764/111 (2)/ 08 -80 (प्रा0आ0) /07 दि0 24/3/08
TS Amount (lakhs) : 368.43 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
370.00
Resanction Cost :
370.00
Tentative Cost :
370.00
Exp. Upto Last Fy : 160.81
For CFY 2024-2025
Remaining : 209.19
Demand : 150.00
Allotment : 30.00
Exp in CFY : 120.01
Total Up to Date Exp : 280.82
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 70 %
Sanction on :
16 years 3 months ago
24 Mar 2008
Tentative Completion date:
4 months 1 week from now
30 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 17: AIP Govt of India
Bottelneck: no issue
7 किमी0 में पहाड़ कटान का कार्य एवं 4 किमी0 में पार्ट -।। का कार्य पूर्ण । शेष प्रगति में है। -- as on 04-Jul-2024
Physical Peramenters