Work Profile Report [20W40]
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : शा0 सं0 764/111 (2)/ 08 -80 (प्रा0आ0) /07 दि0 24/3/08
TS Amount (lakhs) : 368.43 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
370.00
Resanction Cost :
370.00
Tentative Cost :
370.00
Exp. Upto Last Fy :
329.10
For CFY 2025-2026
Remaining :
40.90
Demand :
27.59
Allotment :
12.60
Exp in CFY :
12.60
Total Up to Date Exp :
341.70
Construction Started
Sanction on : 17 years 8 months ago
24 Mar 2008
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
70 %
Tentative Completion date on : 10 months 2 days from now
18 Oct 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
स्वीकृत धनराशि में 7 किमी0 में मार्ग निर्माण कार्य पूर्ण। मुआवजा वितरण का कार्य किया जा रहा है. -- as on 15-Dec-2025
Assets :