Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 3.000 | 9 | 4.000 | 0.000 |
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
20W40 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0 764/111 (2)/ 08 -80 (प्रा0आ0) /07 दि0 24/3/08
TS Amount (lakhs) : 368.43 Lacs
Financial Detail
Sanction Cost : 370.00 Lacs
Resanction Cost : 370.00 Lacs
Exp. Upto Last Fy : 160.81 Lacs
For CFY 2024-2025
Remaining : 209.19 Lacs
Demand : 150.00 Lacs
Allotment : 30.00 Lacs
Exp in CFY : 44.64 Lacs
Total Up to Date Exp : 205.46 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
16 years 1 month ago
24 Mar 2008
Tentative Completion date:
3 years 10 months from now
31 Mar 2028
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 17: AIP Govt of India
Bottelneck: no issue
4 किमी0 में पहाड़ कटान का कार्य एवं 3 किमी0 में पार्ट -।। का कार्य पर्ण । शेष प्रगति में है। -- as on 30-Mar-2024
Physical Peramenters