Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
20W410 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनसदेश संख्या 1430/।।।(2)/21-45(एम.एल.ए.)/2017 टी0सी0 दि0 02 जून 2021
TS Amount (lakhs) : 54.39 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
64.26
Resanction Cost :
64.26
Tentative Cost :
64.26
Exp. Upto Last Fy : 49.53
For CFY 2024-2025
Remaining : 14.73
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 49.53
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
02 Jun 2021
Tentative Completion date:
7 months 3 weeks from now
10 Mar 2025
Actual Completion Date:
1 year 3 months ago
27 Mar 2023
Remark
Bottelneck: no issue
स्वीकृति के अन्तर्गत कार्य पूर्ण। -- as on 30-Mar-2024
Physical Peramenters