Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 2 | 2 | 0 | 2 | 0 | 0 |
Span of Bridges [m] | 72 | 72 | 0.000 | 72 | 0.000 | 0.000 |
20W492 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-FILE N0. -47106 DT. 21-02-2023
TS Amount (lakhs) : 18.72 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
18.72
Resanction Cost :
18.72
Tentative Cost :
18.72
Exp. Upto Last Fy : 0.30
For CFY 2024-2025
Remaining : 18.42
Demand : 14.00
Allotment : 7.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.30
Survey work done
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 15 %
Sanction on :
1 year 4 months ago
21 Feb 2023
Tentative Completion date:
1 year 5 months from now
31 Dec 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डी0 पी0आर0 गठन हेतु निविदा आमंत्रित की गयी थी। स्थल पर अतिक्रमण होने, वनभूमि /राजस्व भूमि का आपसी विवाद होने के कारण अनुबंध गठन की कार्यवाही में विलम्ब हो रहा है। दि0 20.08.2023 को अतिक्रमण हटाये जाने की कार्यवाही की गयी थी, लेकिन आंशिक भाग पर ही अतिक्रमण हटाया जा सका । पुनः माह दिसम्बर के अंतिम सप्ताह में आपसी बैठक / वार्ता द्वारा सहमति होने पर अतिक्रमण हटा लिया गया है। राजस्व विभाग / वन विभाग के साथ पुनः दि0 21.02.2024 को सयुक्त निरीक्षण कर लिया गया है, रिर्पोट पाप्त हो गई है। कंसल्टेंट द्वारा अपने पत्र सं0 - टी0सी0एस0/2024-25/015 दि0 23.04.2024 से निविदा की वैधता न बढ़ाए जाने के संबंध में सूचना दी गई है। QCBS आधारित निविदा में द्वितीय प्रतिभागी को पत्र प्रेषित किया गया है। एम0ओ0यू0 फैस्टल कंसल्टिंग इ0 प्रा0 लि0 के नाम दि0 12.06.2024 को गठित कर लिया गया है। ऐजेन्सी द्वारा जियो टेक्निकल सर्वे का कार्य कर लिया गया है। स्थल चयन प्रपत्र तैयार करने हेतुु आवश्यक डाटा स्थल से ले लिए गये है। ऐजंसी के भू- वैज्ञानिक द्वारा स्थलीय निरीक्षण भी कर लिया गया है। -- as on 01-Jul-2024
Physical Peramenters