Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 11.5 | 11.5 | 0.000 | 11.5 | 11.500 | 10.000 |
20W501 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता (विभागाध्यक्ष) लो0 नि0 वि0 उत्तराखण्ड देहरादून के पत्र संख्या 895/07 याता0-पी0एम0जी0एस0वाई0-नि0।।। दि0 16.05.2023
TS Amount (lakhs) : 212.21 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
212.21
Resanction Cost :
212.21
Tentative Cost :
212.21
Exp. Upto Last Fy : 52.82
For CFY 2024-2025
Remaining : 159.39
Demand : 159.00
Allotment : 32.06
Exp in CFY : 31.95
Total Up to Date Exp : 84.77
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 90 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 weeks 1 day from now
09 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
10 किमी0 में कार्य पूर्ण । 10 काॅजवे का सुधार कर लिया गया है। तथा 2 काजवे में सुधार कार्य प्रगति में है। -- as on 29-Jun-2024
Physical Peramenters