Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 58 | 58 | 30.000 | 28 | 28.000 | 0.000 |
20W535 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2451/।।।(2)/ 23-01(प्रा0आ0)/2019 दि0 21.07.2023
TS Amount (lakhs) : 894.36 Lacs
Financial Detail
Sanction Cost : 1,020.52 Lacs
Resanction Cost : 1,020.52 Lacs
Exp. Upto Last Fy : 500.61 Lacs
For CFY 2024-2025
Remaining : 519.91 Lacs
Demand : 393.49 Lacs
Allotment : 200.00 Lacs
Exp in CFY : 173.00 Lacs
Total Up to Date Exp : 673.61 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
9 months 4 weeks ago
21 Jul 2023
Tentative Completion date:
5 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्वीकृत क्रैश बैरियर , लम्बाई 16800 मी0 के सापेक्ष 14600 मी0 लम्बाई में क्रैश बैरियर लगाये जाने का कार्य पूर्ण । शेष कार्य प्रगति पर है। -- as on 07-May-2024
Physical Peramenters