Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 75.13 | 75.13 | 38.000 | 37.13 | 37.130 | 0.000 |
20W536 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 2937/।।।(2)/ 23-01(प्रा0आ0)/2019 दि0 11.08.2023
TS Amount (lakhs) : 416.79 Lacs
Financial Detail
Sanction Cost : 416.79 Lacs
Resanction Cost : 416.79 Lacs
Exp. Upto Last Fy : 218.04 Lacs
For CFY 2024-2025
Remaining : 198.75 Lacs
Demand : 198.75 Lacs
Allotment : 160.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 218.04 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 65 %
Sanction on :
9 months 1 week ago
11 Aug 2023
Tentative Completion date:
5 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्वीकृत क्रैश बैरियर , लम्बाई 3795 मी0 के सापेक्ष 3765 मी0 लम्बाई में क्रैश बैरियर लगाये जाने का कार्य पूर्ण । शेष कार्य प्रगति पर है। -- as on 07-May-2024
Physical Peramenters