Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.25 | 5.25 | 5.250 | 0 | 0.000 | 0.000 |
20W537 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन के ई फाईल संख्या - 48456 दि0 10.08.2023
TS Amount (lakhs) : 15.63 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
15.63
Resanction Cost :
15.63
Tentative Cost :
15.63
Exp. Upto Last Fy : 8.48
For CFY 2024-2025
Remaining : 7.15
Demand : 7.15
Allotment : 6.85
Exp in CFY : 6.85
Total Up to Date Exp : 15.33
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 1 week ago
10 Aug 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
4 months 2 weeks ago
03 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण । -- as on 04-Jul-2024
Physical Peramenters