Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.25 | 5.25 | 5.250 | 0 | 0.000 | 0.000 |
20W537 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन के ई फाईल संख्या - 48456 दि0 10.08.2023
TS Amount (lakhs) : 15.63 Lacs
Financial Detail
Sanction Cost : 15.63 Lacs
Resanction Cost : 15.63 Lacs
Exp. Upto Last Fy : 8.48 Lacs
For CFY 2024-2025
Remaining : 7.15 Lacs
Demand : 7.15 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 6.85 Lacs
Total Up to Date Exp : 15.33 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
9 months 1 week ago
10 Aug 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण । दायित्वों का भुगतान शेष है। -- as on 22-Apr-2024
Physical Peramenters