Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 0.000 | 8 | 4.000 | 0.000 |
20W551 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.o. E File No. 51659 dt. 19.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 448.49 Lacs
Resanction Cost : 448.49 Lacs
Exp. Upto Last Fy : 0.10 Lacs
For CFY 2024-2025
Remaining : 448.39 Lacs
Demand : 250.00 Lacs
Allotment : 50.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.10 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
4 months 1 hour ago
19 Jan 2024
Tentative Completion date:
1 year 1 week from now
31 May 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में है। -- as on 30-Mar-2024