Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8.6 | 8.6 | 0.000 | 8.6 | 8.600 | 8.600 |
20W554 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता का कार्यालय पत्रांक 191/14 याता0(क)-उ0/2023 दि0 09.02.20024 से अनुमोदित ।
TS Amount (lakhs) : 143.71 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
143.71
Resanction Cost :
143.71
Tentative Cost :
143.71
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 143.71
Demand : 143.71
Allotment : 50.00
Exp in CFY : 44.93
Total Up to Date Exp : 44.93
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
5 months 1 week ago
09 Feb 2024
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण । -- as on 14-Jul-2024
Physical Peramenters