Work Profile Report [22W1255]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 2614/III (2)/21-56(MLA)2017 TC, dt. 10.08.2021
TS Amount (lakhs) : 77.36 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
77.36
Resanction Cost :
77.36
Tentative Cost :
77.36
Exp. Upto Last Fy :
60.46
For CFY 2024-2025
Remaining :
16.90
Demand :
15.00
Allotment :
16.76
Exp in CFY :
16.76
Total Up to Date Exp :
77.22
Work completed
Sanction on : 3 years 4 months ago
10 Aug 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 10 months ago
11 Feb 2023
Actual Completion Date : 1 year 11 months ago
01 Jan 2023
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: