Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.825 | 0.825 | 0.000 | 0.825 | 0.000 | 0.000 |
22W1303 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश संख्या 2079/(1)/।।। (2)/21-34 (प्रा0आ0)2017, दिनाॅक 20.07.2021
TS Amount (lakhs) : 42.57 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
42.57
Resanction Cost :
42.57
Tentative Cost :
42.57
Exp. Upto Last Fy : 14.07
For CFY 2024-2025
Remaining : 28.50
Demand : 15.00
Allotment : 15.00
Exp in CFY : 1.56
Total Up to Date Exp : 15.63
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
20 Jul 2021
Tentative Completion date:
2 years 2 months ago
15 May 2022
Actual Completion Date:
2 years 2 months ago
15 May 2022
Remark
Bottelneck: no issue
कार्य पूर्ण । -- as on 13-Jul-2024