Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 0.000 | 3.5 | 0.600 | 0.000 |
22W1358 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT-PART (2) 1/123108 E-Fine No. 53170, dt. 19-05-2023
TS Amount (lakhs) : 44.98 Lacs
Financial Detail
Sanction Cost : 44.98 Lacs
Resanction Cost : 44.98 Lacs
Exp. Upto Last Fy : 40.49 Lacs
For CFY 2024-2025
Remaining : 4.49 Lacs
Demand : 4.49 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 40.49 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
1 year 34 minutes ago
19 May 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 03-Aug-2023
Physical Peramenters